At Risk of Delay

No.ActionProposed OutputSMP DeadlineStatusProgressASI
11Commence delivery of phase 1 of Cork Area Commuter Rail Programme.2024 Kent Station platform completed. 2025 Midleton double-tracking completed.2025 Q4At Risk of DelayKent Station: Construction Contract was awarded at the end of March 2023. The contractor is continuing works to the new Platform 5 Access. Midleton Double-Tracking: At risk of delay to 2026 in line with the National Recovery and Resilience Plan timeline.Shift
18Expand the operation of bike share schemes (including electric bikes) in cities.2022 Bike share scheme operational in Waterford. 2024 Expand the operation of bike share schemes (including electric bikes) in cities.2024 Q4At Risk of DelayWaterford bike share commenced operation in July 2022. Current contract for TFI bikes extended by 1 year to consider overall approach in line with development of National Policy Statement on Shared Mobility Hubs.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
22Commence delivery of BusConnects network redesign in the five cities. (Complements CAP actions 239, 240)2022 Network of Cork and Galway services finalised. 2023 Network of Limerick and Waterford services finalised. 2025 Dublin BCNR Phases 1-11 implemented (phased implementation on an annual basis). Cork BCNR fully implemented. Galway BCNR fully implemented.2025 Q4At Risk of DelayThe Cork BusConnects network was published in June 2022. Implementation planning is now ongoing which will require various infrastructure interventions across Cork City to facilitate the new routes, in addition to new fleet and depot space. The NTA published its finalised new bus network for Galway and Limerick in Q4 2023 and implementation planning for both networks has commenced. Waterford network were published on the 8th of July 2024 for public consultation and will run to mid-August. Next phase of Dublin network redesign to rollout in Q4 2024, subject to driver availability.Shift
24Commence delivery of MetroLink. (Complements CAP action 247)2022 Railway Order application submitted. 2025 MetroLink enabling works contracts commenced (subject to Government approval and planning consent).2025 Q4At Risk of DelayAn Bord Pleanála commenced an Oral Hearing in relation to Metrolink on February 19th, which finished on March 28th. Dependent on the outcome of the planning process, and the lack of a successful legal challenge, construction of MetroLink is earmarked to commence over the coming years. Additionally, a Project Director was appointed in June 2024 in a major milestone for the project.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
31Develop a model for bike share schemes (including the potential for electric bikes) in regional growth centres and key towns.2023 Model developed. 2024 Pilots introduced.2024 Q4At Risk of DelayMicro-mobility strategy detailing how this system will be operated and managed has been prepared, and will be further developed in alignment with Action 87. The implementation of pilot projects is unlikely to happen in 2024 due to the time required to design and tender the required infrastructure and services.Shift
37Upgrade regional rail lines.2022 Track renewal works completed on Ballybrophy to Limerick line. 2025 50% of programme of upgrade (and elimination) to user worked level crossings on Ballybrophy to Limerick line. 25% of track improvement works on Limerick to Waterford line. 20% of programme of upgrade (and elimination) to user worked level crossings on Limerick to Waterford line.2025 Q4At Risk of DelayThe track renewal works due on the Ballybrophy to Limerick line were complete in 2022. Iarnród Éireann have commenced exploratory works on the remaining elements of the action due for completion by 2025. Fulfilling the stated objectives for the Ballybrophy to Limerick and Limerick to Waterford lines is subject to funding availability.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
83Rollout of Next Generation Ticketing (NGT) on all PSO bus services operating in Dublin.2023 NGT contract awarded 2025 Implementation of first bus route with NGT.2025 Q4At Risk of DelayA Framework Agreement was signed in Q1 2024. Planning will now commence with the appointed Service Provider. Despite there being a delay in awarding the NGT contract, it is not currently anticipated that this will have a negative effect on overall delivery of the action.Shift
85Rollout Next Generation Bus Automated Vehicle Location System (AVL).AVL system rolled out2025 Q4At Risk of DelayDesign work complete. Delivery timeline under review.Shift

Ongoing

No.ActionProposed OutputSMP DeadlineStatusProgressASI
04Continue to protect and renew road infrastructure for all road users including sustainable mobility users.OngoingOngoingOngoingShift
46Accelerate sustainable mobility plans for schools through: - Expansion of Cycle Right Training in primary and post- primary schools. - Rollout of Safe Routes to Schools Infrastructure Programme. - Complete review of the School Transport Scheme and identify measures to improve sustainability of school transport scheme. (CAP action 235)Annual Additional 5,000 pupils per year trained under Cycle Right programme. 2022 Safe Routes to School Infrastructure Programme commenced in 170 schools. Measures to improve sustainability of School Transport system identifiedOngoingOngoingThe Cycle Right element of this action was delivered successfully in 2023 and is continuing in 2024. Rollout of the SRTS Infrastructure Programme continued in 2023 and to date in 2024. A review of the School Transport System has been completed and measures have been identified to improve sustainability.Shift
47Explore potential of road-user charging measures through the Better Road User Charging Evaluation (BRUCE) study. (CAP action 259)Draft implementation plan published.2025 Q4OngoingA draft Alignment and Pathways report has been received. Awaiting outcomes from the Department’s national demand management strategy (“Moving Together”) and the NTA’s GDA Demand Management Strategy as it may be necessary to update.Avoid
56Fund local authorities to upgrade existing active travel infrastructure to meet safety, permeability and design standards.OngoingOngoingOngoingThis action was achieved in 2023 and 2024 with funding allocations made to all 31 local authorities for new and improved active travel infrastructure. 2025 levels funding will be dependent on the annual Estimates process.Shift
No.ActionProposed OutputSMP DeadlineStatusProgressASI
61Continue a joint approach in respect of the Design Manual for Urban Roads and Streets (DMURS) to ensure more widespread and consistent implementation. (HfA Policy Objective 21.1)OngoingOngoingOngoingSupport and Development relating to DMURS is ongoing with work underway in relation to ‘Reallocation of Street Space’ and to commence in relation to ‘Landscaping’.Avoid
62Deliver an average of 60 road safety improvement schemes and fund an average of four minor realignment schemes on national roads per year, to create forgiving roadsides, self- explaining roads, and a safe environment for vulnerable road users. (RSS action 2)AnnualOngoingOngoingSeven Minor Safety Projects reached completion in 2023 and over 100 Safety Improvement Schemes were completed, which included three key junction improvement schemes.Shift
67Provide training to designers, project managers, engineers and local authorities on the delivery of safe designs based on the Design Manual for Urban Roads and Streets (DMURS) and the National Cycle Manual (NCM). (RSS action 64)2022 Q4OngoingTraining to be developed through appropriate national training groups and third level institutions.Shift

Figure from page 57

Figure from page 57

Prepared by the Department of Transport gov.ie/transport

Pages 51–57 · View in original PDF