SMP Action Status Updates
This report sets out the progress made in the three years since the Policy was launched in April 2022, as well as an update on the implementation of actions since the last report was published in August 2024.
Completed
50.5%
SMP Progress to end of April
On Schedule 2025
6.6%
Delay Anticipated
16.5%
Ongoing
5.5%
Delayed
Modified
15.4%
5.5%
Figure 1: Action delivery status to end April 2025
It should be noted that the action status categorisation, as outlined in Figure 1 and the remainder of the report, is by necessity an imperfect tool. For example, where actions consist of several sub-actions, a small delay to only one sub-action will render the full action incomplete. This often misrepresents the level of progress that has been delivered across
an action, particularly where the remaining sub-actions are on schedule for delivery or are fully completed. Accordingly, this report seeks to provide a detailed account of the delivery of each action, as set out below and in Annex 1. For those actions that are delayed, this report seeks to reflect the specific elements that have led to delay.
For ease of reference, the following explains the action status categories in line with Figure 1:
| Table 1 Category | Action Status Categories Description |
|---|---|
| Complete | The action and related outputs in the SMP Action Plan have been fully completed. |
| On Schedule | The action and related outputs in the SMP Action Plan are due for delivery at the end of 2025 and are currently expected to be delivered on time. |
| Ongoing | The action and related outputs in the SMP Action Plan refer to areas of work which take place annually or on an ongoing basis. |
| Modified | The original action in the SMP Action Plan has progressed but has diverged in scope and/or direction impacting timescales and output definitions. This reflects the need for agility and adaptability. This is a new category in the Year Three report. |
| Delayed | The action and related outputs in the SMP Action Plan are past their scheduled date for delivery and have not yet been fully completed. |
| Delay Anticipated | The action and related outputs in the SMP Action Plan are due for delivery in Q4 2025 and it is not now expected that they will be fully delivered by that date. This category was referred to as “At Risk of Delay” in previous reports. |
Pages 8–9 · View in original PDF