SMP Action Status Update
SMP Action Progress to end April 2023
On Schedule 48 Actions
Complete 7 Actions
Delayed 13 Actions
At Risk of Delay 8 Actions
Ongoing 5 Actions

Figure from page 6
Complete 19%
At Risk of Delay 9%
Figure 1: Action delivery status to the end of April 2023
Full details of progress across all 91 actions may be found in Annex I. For ease of reference, the following provides a summary of the highlighted action categories in Figure 1
Page 6 · View in original PDF