Goal 3: Expand availability of sustainable mobility in metropolitan areas.

ACTIONLEADSUPPORTDEADLINEOUTPUTINTERIM MILESTONES
14. Deliver additional walking and cycling infrastructure projects in the five cities.NTADoT, LAs2030400kms of new/ upgraded walking and cycling infrastructure in the five cities.2027 interim target - 150km of new/ upgraded walking and cycling infrastructure in the five cities.
15. Expand the provision of shared micromobility in the five cities.NTADoT2028Expanded shared mobility schemes in place in all five cities, including enhanced e-bike and optional scooter provision.Q4 2026 – Tendering complete for expanded shared mobility schemes in Cork, Waterford, Limerick, Galway, and service roll-out commenced Q2 2027 – Contract renewal process complete in Dublin. Q3 2027 – New bikes introduced in Dublin.
16. Advance construction of BusConnects Dublin Core Bus Corridors.NTADoT2030Four core bus corridors completed.Q3 2026 – Commencement of construction for Ballymun/Finglas to city corridor. Q2 2028 – Completion of Liffey Valley to city corridor.
ACTIONLEADSUPPORTDEADLINEOUTPUTINTERIM MILESTONES
17. Commission an independent feasibility study into continuing MetroLink from the city to south-west Dublin, as part of the upcoming review of the GDA transport strategy.NTADoTQ4 2027Feasibility study completed.
18. Commence construction of first Sustainable Transport Corridor as part of Cork BusConnects, subject to planning permission.NTADoT2030First BusConnects Cork Sustainable Transport Corridor commenced construction.Q4 2026 – Planning applications lodged for Sustainable Transport Corridors in Cork.
19. Commence construction of first Sustainable Transport Corridors as part of BusConnects Galway, subject to planning permission.NTADoT2030First BusConnects Galway Sustainable Transport Corridor commenced construction.Q4 2027 – Planning applications lodged for Sustainable Transport Corridors in Galway.
20. Commence construction of MetroLink.NTADoTQ4 2027Construction commenced.Q1 2026 – Procurement process commenced. Q3 2027 – Awarding of main civils contracts.
ACTIONLEADSUPPORTDEADLINEOUTPUTINTERIM MILESTONES
21. Delivery of series of new track passing loops and platforms to boost the Irish rail network’s resilience and capacity, as set out in the Rail Project Prioritisation Strategy and contributing to the recommendations in the All-Island Strategic Rail Review.NTADoT, IÉ2030Delivery of a series of new track passing loops and platforms to boost the rail network’s resilience and capacity.Q1 2027 – Commencement of these works.
22. Complete implementation of Cork Area Commuter Rail Programme Phase 1.NTADoT, IÉQ4 2026Delivery of the Kent Station Through Platform. Twin tracking between Glounthaune and Midleton. Comprehensive upgrade of signalling and communications systems.
23. Commence construction of Cork Area Commuter Rail Programme Phase 2.NTADoT, IÉ2029Commence construction of new train stations at Blackpool and Dunkettle, as well as initial electrification works and depot construction.Q2 2026 – Lodgement of Planning applications for two stations. Q1 2027 – Secure Approval Gate 1 consent from Government for the Programme.
ACTIONLEADSUPPORTDEADLINEOUTPUTINTERIM MILESTONES
24. Open new Waterford Plunkett Station and Transport Hub.IÉDoT, DHLGH, NTAQ2 2027Construction of a transport hub and railway station at the centre of the North Quays Strategic Development Zone.
25. Complete upgrade works in Oranmore rail station.NTADoT, IÉ, DHLGHQ4 2027Construct additional platform and track passing loop, increasing capacity on the line between Athenry and Galway.
26. Completion of Ceannt Station in Galway.NTADoT, IÉ, DHLGHQ3 2026Number of platforms increased from two to five and customer facilities improved.
27. Construct new rail station in Moyross.NTADoT, IÉ2030Construct a new rail station in the Moyross area of Limerick.Q4 2026 – Conduct tendering. Q2 2027 – Commence construction.
28. Commence construction of Luas Finglas, subject to Enforceable Railway Order.NTADoT2029Construction of Luas Finglas commenced.Q4 2027 – Commence main construction contract procurements.
29. Implement consistent, evenly spaced, clock- faced timetables on Intercity and Commuter Rail Services outside of Peak Periods throughout the week.NTADoT2029Revised rail timetables driven by demand and travel patterns.Annual timetable revisions in line with operating requirements.