Complete
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 01 | Develop and publish an annual public transport passenger safety and personal security report and implement measures where appropriate. | 2022 Report developed. 2023 First report published. 2024 and 2025 Annual reports published | 2025 Q4 | The 2023 report was published in March 2024. The 2024 report was published in April 2025. (Available to view at: https:// www.nationaltransport.ie/publications/ nta-security-report-2024/) |
| 02 | Continue awareness campaigns with the aim of promoting inclusivity, courtesy and respect for all when travelling on public transport. | Annual Campaigns | 2025 Q4 | Annual campaigns took place each year from 2022 to 2025. In 2025 the NTA embedded a range of diversity and inclusion communications campaigns in its annual marketing plan. This included the ‘Please offer me a seat’, ‘Prepare Me… As I Am…for Public Transport’, ‘My Journey, My Way’ campaigns and support of users with disabilities with the JAM card. |
| 03 | Continue to protect and renew rail infrastructure through the Infrastructure Manager Multi-Annual Contract (IMMAC). | 2024 Existing IMMAC reviewed. 2025 IMMAC 2025-2029 agreed. | 2025 Q4 | The IMMAC 2026-2030 contract approved by Government and signed by D/Transport and Iarnród Éireann in December 2025. |
| 04 | Continue to protect and renew road infrastructure for all road users including sustainable mobility users. | | Ongoing | This action was delivered on an ongoing basis. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 07 | Further develop camera- based enforcement by the Gardaí, including at junctions and for management of bus/ cycle lanes, building on existing and recent legislation through establishing suitable cross- agency administrative arrangements; and, where any legislative issues are identified, to consider and develop agreed proposals to remedy them. (RSS action 67) | | 2022 Q4 | Report of the associated cross-agency Working Group has been completed and provided to the Department of Transport and presented to the Road Safety Transformation Board. This work has informed the development of the first National Safety Camera Strategy, which was published in April 2026. |
| 08 | Deliver fuelling/charging infrastructure to support operation of zero emission public bus fleet. | Fuelling and charging infrastructure in place for public bus fleet. | 2025 Q4 | Depot electrification works are now complete in Athlone and in Bus Éireann’s Limerick depot, as are the first and second phases of works in Dublin Buses Phibsborough depot and the first phase of works in Dublin Bus’s Summerhill depot. Construction and implementation of the first phases of works in the Dublin Bus depot in Harristown is progressing well, and commencement of electrification works at Bus Éireann’s Galway depot await planning approval from Galway City Council. Tender submissions have been received for the electric bus charging infrastructure and are being reviewed. It is anticipated that the framework will be awarded in Summer 2026 and will serve as the basis for future charger installations rather than continued reliance on standalone procurement processes. |
| 10 | Develop a strategy to transition the Small Public Service Vehicle (SPSV) fleet to lower/zero emission technologies. | Strategy developed and implementation commenced. | 2024 Q4 | Zero Emission Vehicles Ireland was established within the Department of Transport in July 2022. Implementation is ongoing through the eSPSV grant and taxi infrastructure funding. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 14 | Transition Cork, Galway, Limerick and Waterford metropolitan area PSO bus services to low/ zero emission bus fleet. (Complements CAP action 269) | 40% of fleet transitioned to low/zero emission vehicles. | 2025 Q4 | More than 50% of the fleet of 230 PSO urban buses (end-2021 figure used in SMP) in these cities, including 61 hybrids and 61 battery-electric buses. Limerick is the first irish city to have a fully zero- emission urban public bus fleet, while Galway’s PSO urban bus services operated by Bus Éireann are fully low-emission. A further 48 zero-emission battery-electric buses will be ready to join the fleet once further charging infrastructure comes onstream in Galway. |
| 16 | Complete Strategic Rail Review to, inter alia, identify a pathway to appropriate decarbonisation of interurban rail services. (Complements CAP action 285) | Review completed | 2022 Q4 | All-Island Strategic Rail Review published on 31 July 2024. |
| 17 | Develop pedestrian enhancement plans for the five metropolitan areas. | Plans developed | 2023 Q4 | This project commenced at the end of March 2023. Plans for all cities have been developed and stakeholder consultation is complete. |
| 18 | Expand the operation of bike share schemes (including electric bikes) in cities. | 2022 Bike share scheme operational in Waterford. 2024 Expand the operation of bike share schemes (including electric bikes) in cities. | 2024 Q4 | Waterford bike share commenced operation in July 2022. Shared e-bike trial has been launched with 100 e-bikes operational in Cork, and a further 400 being rolled out in the remaining regional cities. New bike stations have been installed in Cork and Limerick with a substantial increase in the usage of the bikes as a result. Additionally, a qualification system for micro-mobility contractors has been established and a tender process for Cork, Galway, Waterford and Limerick is underway, with the objective of further expanding the existing shared micromobility schemes in these cities including through increased provision of electric bikes. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 19 | Deliver additional cycling infrastructure projects in the five cities. (Complements CAP action 233, RSS action 5) | 400 km GDA Network completed or under construction. 200 km Regional Cities Network completed or under construction. | 2025 Q4 | Around 1,000 cycling schemes are in design or implementation across the country. Since 2020, over 1,000 km of new or upgraded active travel infrastructure has been delivered, including almost 150 km in 2025 alone. By the end of 2025, 416km of the GDA Network and 350km of the Regional Cities Network of Active Travel infrastructure are completed or under construction. |
| 23 | Commence delivery of BusConnects Core Bus Corridor Infrastructure Works in the five cities. (Complements CAP actions 241, 242, 243, 244) | 2022 Construction of Salmon Weir cycling and pedestrian bridge commenced as part of BusConnects Galway. Planning process for Cross City Link commenced as part of BusConnects Galway. 2023 Planning process for Dublin Road Scheme commenced as part of BusConnects Galway. On-street construction of Radial Core Bus Corridor Schemes commenced as part of BusConnects Dublin. | 2023 Q4 | The Salmon Weir Bridge opened in May 2023. The Dublin Road Scheme received approval from An Coimisiún Pleanála in Q4 2025. Cross City Link initially received approval from An Coimisiún Pleanála in October 2024 - currently subject to judicial review. All 12 corridor applications under BusConnects Dublin were lodged with An Coimisiún Pleanála which have all received planning permission, though six are subject to ongoing legal challenges. Contracts have been awarded for both the Liffey Valley to City Centre, and Ballymun- Finglas to City Centre Schemes, with view to them entering heavy construction this year. The NTA also expects to commence procurement on the third scheme, Clongriffin to the City Centre, later in 2026. |
| 25 | Increase provision of park and ride/share at transport interchanges. (CAP action 260) | Implementation of GDA Park and Ride Strategy commenced. | 2022 Q4 | Implementation of the GDA Park and Ride Strategy has commenced. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 27 | Develop and implement an active travel infrastructure programme for regional growth centres and key towns outside of the Greater Dublin Area. (Complements CAP action 233, RSS action 5, 40) | 2023 Urban cycle networks developed for all regional growth centres and key towns outside the GDA. 2025 100 km constructed or under construction in regional growth centres and key towns outside the GDA. | 2025 Q4 | Cycle network plans have been developed for all counties, including regional growth centres and key towns. Public consultation on draft plans for 22 counties (outside the GDA) concluded in late 2022. Following revisions, the Strategic Environmental Assessment was completed in Q2 2024, with statutory consultation completed in Q4 2024. The GDA Cycle Strategy was completed in 2023. Over 1,000km of walking and cycling infrastructure is at design stage and approximately 150km was at construction as of end 2025. |
| 29 | Develop and publish a strategic national cycle network. (Complements CAP action 232, RSS action 39) | Network published. | 2022 Q4 | The National Cycle Network (NCN) was published in Q1 2024 and work is ongoing on its delivery. To date, over 600km of NCN related infrastructure has been provided (compared to 330km target by the end of 2025). Signage and branding for this infrastructure has been developed and the rollout of this on sections of the network will commence in 2026. Approximately 500km of NCN related infrastructure is currently in planning or under development to enable the 2030 target of 990km to be achieved. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 32 | Implement an enhanced rural transport system through delivery of Connecting Ireland. (Complements CAP action 245) | Connecting Ireland programme commenced for bus, rail and alternative solution | 2022 Q4 | Over 185 new or enhanced services introduced since commencement in mid- 2022. Phase I in 2022: 38 new and enhanced services implemented. Phase II in 2023: 65 new and enhanced services implemented. Phase III in 2024: 45 new and enhanced services implemented. Phase IV in 2025: 36 new and enhanced services implemented. Over 240 towns and villages have been connected to the public transport network and 300,000 weekly vehicle kilometres have been added to the TFI public transport network. To date the plan has delivered: ● 41 connections to higher education facilities, ● 61 connections to healthcare facilities, and ● 71 connections to existing rail services. The NTA publish quarterly bulletins on the Connecting Ireland programme available to view at the following link: https://www. nationaltransport.ie/connecting-ireland/ |
| 35 | Develop and commence delivery of an enhanced bus stop and bus shelter programme for regional and rural services. (Complements RSS action 71, 72) | 2022 Programme developed. 2025 200 additional bus shelters installed for regional and rural services. | 2025 Q4 | Programme development completed. The target of 200 additional bus shelters by 2025 has been surpassed, with 126 delivered in 2022, 124 in 2023, 195 in 2024 and 68 in 2025. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 36 | Increase provision of local area hackney services in conjunction with development of Connecting Ireland. | 2022 Local Area Hackney Scheme reviewed and local area hackneys developed in line with Connecting Ireland programme for community cars. 2023 Revised subsidised Local Area Hackney Programme introduced based on findings of review. | 2023 Q4 | The subsidised Local Area Hackney Scheme Pilot went live in early 2023. The Pilot has resulted in two candidates being fully licensed. |
| 39 | Establish a Demand Management Unit within the Department of Transport to develop an approach to traffic demand management taking account of the recommendations of the Five Cities Demand Management Study. (Complements CAP actions 250 and 258) | Unit established. | 2022 Q4 | This work is being led by the Department of Transport’s Demand Management Division. |
| 41 | Develop and commence implementation of a programme for secure bicycle parking in key towns and cities plus transport hubs. | 2023 Programme developed. 2025 1,000 secure bicycle parking spaces implemented. | 2025 Q4 | Overall strategy document and implementation programme is complete. Designs are being developed for two Irish Rail locations in Dublin, with a third under consideration. The target for secure bicycle parking spaces has been surpassed, with over 3,200 publicly accessible cycle parking spaces implemented in 2024 alone and an additional 1,800 added in school, campus and hospital grounds. Just under 1,500 cycle parking spaces were implemented in 2025. In addition, an upgrade of existing multistorey facilities is in development. A contract for 300 bike lockers has been awarded and rollout has begun around Dublin. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 42 | Expand Walking and Cycling Index to Cork, Galway, Limerick and Waterford to assess infrastructure; travel behaviour; the impact of walking and cycling; and new initiatives in each city. | Survey expanded to regional cities. | 2023 Q4 | Walking and Cycling Index has been rolled out to the regional cities and regular surveys are underway. Individual reports for 2023 have been prepared and were published in 2024. A new iteration of the Walking and Cycling Index was published in March 2026. These are available at https://www.nationaltransport. ie/planning-and-investment/transport- investment/active-travel-investment- programme/walking-and-cycling- index-2025/. |
| 43 | Review impact of Pilot Bike and E-Bike Upcycling Initiative. | Review published. | 2023 Q4 | Review commissioned by Pobal and was completed in early Q4 2023. Review is available at https://www.pobal.ie/app/ uploads/2023/12/Upcycling-of-Bicycles- and-e-Bikes-Pilot-Initiative-EVALUATION- REPORT .pdf. _ |
| 44 | Expand Smarter Travel Workplaces and Campus Programmes to include: ● Guidance for more types of companies and campus facilities. ● Enhanced toolkit for workplace/campus assessment. ● Support for in-work/in- business/ in-campus cycle use through subsidised cycle provision for trial periods. ● Cycle Friendly Employer Certification. (Complements CAP action 249) | Programmes expanded | 2023 Q4 | Number of Smarter Travel partners has increased and Smarter Travel Mark was successfully launched in May 2023. 150 Smarter Travel Marks had been awarded by May 2026. |
| 45 | Conduct a study to assess incentives to encourage greater use of active travel as a mode of transport, including an assessment of international best practice. | Study completed | 2023 Q4 | Study completed in 2023 as part of the annual estimates process. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 46 | Accelerate sustainable mobility plans for schools through: ● Expansion of Cycle Right Training in primary and post-primary schools. ● Rollout of Safe Routes to Schools Infrastructure Programme. ● Complete review of the School Transport Scheme and identify measures to improve sustainability of school transport scheme. (CAP action 235) | Annual Additional 5,000 pupils per year trained under Cycle Right programme. 2022 Safe Routes to School Infrastructure Programme commenced in 170 schools. Measures to improve sustainability of School Transport system identified. | Q4 2024 | The Cycle Right element of this action was delivered successfully in 2023, 2024 and 2025. The Cycle Right programme continues to expand on an annual basis with the objective of increasing the number of primary school students receiving training by 5000 each year. Rollout of the SRTS Infrastructure Programme continued through 2025 with an additional 105 schools entering the Programme in December. Over 150 schools had projects completed by the end of 2025. A review of the School Transport System has been completed and measures have been identified to improve sustainability. |
| 49 | Expand the Travel Assistance Scheme beyond the GDA. | 2023 Scheme expanded to Cork. 2025 Scheme expanded to Galway, Limerick and Waterford. | 2025 Q4 | The pilot of the Travel Assistance Scheme in Cork started taking bookings in September 2022. The Limerick Travel Assistance Scheme commenced in 2023 and the Waterford Scheme commenced in 2024. Two new Travel Assistants commenced work in Galway in January 2025. |
| 50 | Expand the number of Wheelchair Accessible Vehicles in the SPSV fleet. | WAVs expanded by 25%. | 2025 Q4 | At end March 2026, there were 4,836 WAVs in the SPSV fleet, which represents an expansion of over 25% on the WAVs previously in the fleet. In total, 23% of the current SPSV fleet are WAVs. |
| 51 | Ensure all transport operators are contractually obliged to put in place operational procedures to assist people with mobility difficulties in event of unplanned service disruptions. | Contracts updated | 2022 Q4 | All PSO contracts have been updated to include a requirement for these operational procedures. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 52 | Develop and implement an equitable fares strategy for all applicable subsidised services. | 2022 Strategy developed 2023 Implementation commenced | 2023 Q4 | A Fares Strategy was published in April 2023. Phase 2A and 2B were successfully implemented in April and June 2025 respectively, introducing more integrated and equitable fares in Dublin commuter areas within 50 km of Dublin city centre. |
| 53 | Introduce Young Adult Card on a phased basis. (Complements CAP action 248) | Card introduced | 2022 Q4 | Following initial rollout on PSO services, Young Adult Leap Card (YAC) was implemented on all services in September 2022 and has now moved to Business-as- Usual Operations. Participation in the YAC scheme was initially for 19- to 23-year-olds inclusive; however, in October 2022 the YAC was further extended to include third-level students aged 16 to 18. The scheme was extended to participating commercial bus operators in September 2022. YAC was expanded to include 24 and 25-year-olds under Budget 2024. |
| 54 | Fund the establishment of units within local authorities to implement active travel schemes in accordance with best practice and national design guidance. | Units established | 2022 Q4 | Units have been established in all 31 local authorities. |
| 55 | Establish an infrastructure audit team to review compliance with national design guidance and assess value for money approaches in design and construction. | Audit team established | 2022 Q4 | Arrangements have been put in place allowing for appropriate reviews and assessments. |
| 56 | Fund local authorities to upgrade existing active travel infrastructure to meet safety, permeability and design standards. | Ongoing | Ongoing | €360 million was allocated by the Department of Transport for Active Travel and Greenways projects in 2026. This funding can be used by local authorities for the construction of new infrastructure or the protection and renewal of existing infrastructure. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 58 | Prepare and issue guidelines, under Section 38 (6) of the Road Traffic Act 1994, to road authorities relating to traffic calming measures | Prepare and issue guidelines, under Section 38 (6) of the Road Traffic Act 1994, to road authorities relating to traffic calming measures | 2022 Q4 | Guidelines were completed and issued in Q3 2023. Implementation monitoring will be carried out with further enhancements expected in time. |
| 59 | Update national standards and project management guidelines to facilitate all road users on the national road network including the delivery of public transport facilities. | Standards and guidelines updated | 2022 Q4 | Workstream coordinated by National Guidelines and Standards Group (related to Action 63). Significant work has been done to update standards on national roads around cycling, bus priority measures, and other measures. |
| 61 | Continue a joint approach in respect of the Design Manual for Urban Roads and Streets (DMURS) to ensure more widespread and consistent implementation. (HfA Policy Objective 21.1) | Ongoing | Ongoing | This joint approach between the Department of Housing, Local Government and Heritage, the Department of Transport and related agencies is ongoing. In line with a commitment in the National Human Rights Strategy for Disabled People, a programme has been put in place for the review of DMURS, alongside other standards and guidelines that apply to the public transport network where it interacts with associated built environment with regards to accessibility. |
| 62 | Deliver an average of 60 road safety improvement schemes and fund an average of four minor realignment schemes on national roads per year, to create forgiving roadsides, self-explaining roads, and a safe environment for vulnerable road users. (RSS action 2) | Annual | Ongoing | Road safety improvement schemes progressed as planned in 2025. In 2026, further progress will be made on safety initiatives within the motorway network in line with funding commitments. Three minor projects on national roads were completed in 2025. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 63 | Establish a department-led standing coordination group to oversee Guidelines and Standards for roads, traffic, cycling and active travel to ensure: ● Safe System Approach ● Consistency ● Quality/Audit ● Education/Training (RSS action 54) | | 2022 Q4 | Group established and work underway. |
| 64 | Update the National Cycle Manual (NCM) to incorporate updated cycle scheme design guidance aligned with the safe system approach including appropriate training. (RSS action 55) | | 2022 Q2 | A finalised version of the National Cycle Manual (NCM), now known as the Cycle Design Manual, was published in Q3 2023. Training was carried out in Q4 2023. |
| 65 | Review and make recommendations on facilitating cyclists and pedestrians at junctions, including measures that do not require powered traffic signals. (RSS action 56) | | 2022 Q4 | The review was completed in Q2 2025. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 67 | Provide training to designers, project managers, engineers and local authorities on the delivery of safe designs based on the Design Manual for Urban Roads and Streets (DMURS) and the National Cycle Manual (NCM). (RSS action 64) | | 2022 Q4 | Training has been delivered on the Cycle Design Manual through a series of Webinar hosted by the Institute of Engineers Ireland (IEI). The information which was presented is now available on the IEI website. Training has also been delivered on DMURS through a series of webinars hosted by the IEI and is also now available on their website. Aspects of DMURS have now been integrated into planning, civil engineering, architecture and urban design courses in numerous universities around Ireland, including: UCD, TU Dublin, University of Limerick, Maynooth, Cork Institute of Technology, Atlantic Technological University, Munster Technological University and South East Technological University. Further training may be considered as the need arises and will be developed through appropriate national training groups and third level institutions. |
| 68 | Develop and implement a public engagement strategy to promote the benefits of sustainable mobility and raise public awareness of options. | Engagement strategy developed | 2022 Q4 | The Public Engagement Strategy was published in Q2 2024 and is available at https://www.gov.ie/en/department- of-transport/publications/public- engagement-strategy/. |
| 69 | Develop and publish an annual National Household Travel Survey. | First survey published and annual updates published thereafter. | 2023 Q4 | This now takes place on an annual basis. The 2022, 2023 and 2024 National Household Travel Surveys are complete and are available at: https://www. nationaltransport.ie/planning-and- investment/transport-modelling/national- household-travel-survey/. Data collection for the National Household Travel Survey 2025 is complete. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 70 | Establish a Leadership Group to oversee implementation of the Policy and delivery of the action plan. | Leadership Group established | 2022 Q4 | Leadership Group established in May 2022. The Group met on a monthly basis in the set-up phase, moving to quarterly meetings from January 2023 onwards. |
| 71 | Convene a National Sustainable Mobility Forum to engage with stakeholders on progress in relation to the Policy. | Forum established | 2022 Q4 | The third annual Forum took place across four sessions in May 2025, with two sessions taking place online and two in person in Galway and Dublin. |
| 73 | Develop and update appraisal guidance and appraisal review processes based on the most relevant and applicable evidence and methodological advances in the sustainable mobility area. | Appraisal guidance updated to replace existing Common Appraisal Framework. | 2022 Q4 | Finalised appraisal guidance was published in June 2023. |
| 74 | Establish a network and mechanisms to advise on, agree and focus resources towards research priorities that provide an evidence base for implementation of the Policy, drawing on national and international best practice. | Network and mechanisms established | 2022 Q4 | Network and mechanisms have been established. |
| 76 | Ensure that the statutory reviews of the Regional Spatial and Economic Strategies include an analysis of land use development potential based on accessibility to each region’s proposed core public transport network. | Review of RSES for the Eastern and Midland Region commenced. | 2025 Q4 | Following completion of the National Planning Framework (NPF), work on the RSES Review process commenced. A pre- draft paper was published in March 2026 as part of the public consultation process. |
| 79 | Develop section 28 Guidelines for Planning Authorities on Sustainable and Compact Settlement Guidance (SCSG) including guidance on housing typologies to facilitate innovative approaches to medium and higher densities. (HfA Policy Objective 11.2) | Guidelines developed | 2022 Q4 | Guidelines have been published and issued to Local Authorities. |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 80 | Establish a working group of the DHLGH, the D/ Transport, NTA and LDA to consider opportunities for transport led development in our major urban centres. (HfA Policy Objective 26.1) | | 2021 Q4 | A Working Group was established in December 2021 to consider opportunities for transport orientated development (TOD) in the five cities and to also review opportunities for better integration of land use and transport in regional centres. The ‘Opportunities for Transport Orientated Development (TOD) in Major Urban Centres - Dublin Study’ was published in June 2023. It identified 14 potential TOD locations identified close to existing or proposed high-capacity public transport in Dublin for the phased delivery of approximately 130,000 residential units and mixed-use development. In 2024 and 2025, the working group continued considering further potential TOD opportunities. Reports on Cork, Limerick, Galway, Waterford and the Eastern Region are at finalisation stage and will be brought to Cabinet shortly for information and publication in 2026, subject to Government approval. |
| 81 | Require all transport operators and mobility service providers to provide open data for mobility services across Ireland. | Contracts updated | 2023 Q4 | Mobility data enabling journey planning and real-time passenger information is provided by NTA systems or by operators under contractual requirements. |
| 84 | Rollout new multi-modal National Journey Planner. | Planner rolled out | 2022 Q4 | The TFI Live application was launched in February 2023. Key features include: ● Access real-time departure information for Bus Éireann, Dublin Bus, Go Ahead Ireland, Luas and Iarnród Éireann Irish Rail services ● Select your origin and destination to find the best route for your journey ● Search for timetables and maps ● Save your favourite journeys, departures and timetables |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 86 | Develop National Consolidated Customer Contact Centre for Transport. | Centre developed | 2025 Q4 | The first phase of this project was rolled out on 17 September 2024 with Bus Éireann. This was followed by Irish Rail on 22 October and Dublin Bus on 10 December 2024. Go Ahead went live in January and Luas in February 2025 so all major PSO operators are now using the TFI customer contact centre. The NTA migrated over to new centre in March 2025. |
| 88 | Develop a range of simplified and more equitable ticketing solutions to incentivise the use of public transport including fare structures, concessionary fares and tax- based incentives. | Strategy developed | 2022 Q4 | This was completed as part of the wider effort to develop a Fares Strategy under Action 52, which has also now been completed. The rollout of this strategy continued with Phase 2A and 2B launched in 2025, including revisions to TaxSaver tickets. |
| 89 | Legislate to permit the use of PPTs on public roads. (Complements CAP action 237, RSS action 134) | Legislation passed | 2022 Q3 | The Road Traffic and Roads Act 2023 was enacted in June 2023. Relevant sections for PPTs were commenced on 20 May 2024. |
| 90 | Regulate to ensure the safe use of and minimum safety and design requirements for PPTs. | Regulation introduced | 2023 Q4 | Full suite of regulations commenced on 20 May 2024: ● The Road Traffic (Electric Scooters) Regulations 2024 (S.I 199 of 2024) ● The Road Traffic (Signs) Regulations 2024 (S.I 200 of 2024) ● The Road Traffic (Traffic and Parking) (Amendment) Regulations 2024 (S.I 222 of 2024) ● The Road Traffic (Use of Powered Personal Transporters) Regulations 2024 (S.I 224 of 2024) ● The Road Traffic Act 1994 (Detention of Powered Personal Transporters) Regulations 2024 (S.I 223 of 2024) ● The Road Traffic Act 2010 (Part 3) (Fixed Charge Ofef nces) Regulations 2024 (S.I 227 of 2024), |
| No. | Action | Proposed Output | SMP Deadline | Progress |
|---|
| 91 | Examine the feasibility of utilising bus mounted cameras to detect and enforce illegal parking in bus lanes and if appropriate make recommendations for implementation. (RSS action 122) | | 2022 Q4 | A report on this action was completed by the NTA and presented to the Road Safety Transformation Partnership Board in November 2023. Along with work by TII in relation to speed cameras, this report formed key input into the published National Safety Camera Strategy, which was led by TII with input from key stakeholders across the Transport and Justice sectors. |
Pages 18–34 · View in original PDF