Network Development

Figure from page 34
National Cycle Network Plan
Network Development
Development of the NCN corridors was based on an iterative process, summarised in Figure 4.1 and outlined in detail in this section.

Figure 4.1: Summary of Network Development Process
Key assumptions that were central to defining the network were as follows:
Nodes are the towns, settlements or other key destinations which represent a start, end or layover point on the NCN. Three types of nodes were defined, as follows:
Primary node – Consisting of cities and / or large towns with a population of over 20,000 ─ people (towns with over 10,000 were also considered in areas which were more sparsely populated). These represent an NCN start or end point.
Secondary node – Consisting of medium sized towns with a population of between 10,000 ─ and 20,000 people (plus a selection of smaller towns in sparsely populated areas with populations of between 5,000 and 10,000). Major tourist attractions located outside urban areas were also included, and / or Major transport hubs. These represent an NCN start or end point.
Other nodes – Consisting of small towns and settlements, strategic destinations (e.g. transport ─ hubs, centres of education, centres of employment, leisure destinations, and tourist destinations).
Some exceptions to these classifications were made in areas that are remote and do not have the population threshold, to ensure an even and national spread of coverage.
Connections were defined as initial ‘straight line’ links between nodes. Following more detailed assessment of the opportunities presented by each link, a corridor between nodes was defined. Corridors are proposed only at an indicative level and provide a broad alignment within which there may be several potential routes. An options assessment exercise will be required to test the
National Cycle Network Plan
potential routes within a corridor against a series of criteria to define the preferred route. This options assessment exercise does not form part of the current project and will be undertaken as part of the roll out of the NCN.
An overview of each step in defining the NCN is presented in the following sections.
Step 1 – Define Destinations
Using the criteria outlined above, the key destinations for the NCN were identified, as outlined in Table 4.1 and Table 4.2.
Table 4.1: Primary NCN Nodes
| Primary NCN | Basis for inclusion | ||
|---|---|---|---|
| Nodes | |||
| Armagh | NI connection point close to border (may depend on NI greenway strategy) | ||
| Athlone | >20,000 population | ||
| Balbriggan | >20,000 population | ||
| Ballina | >10,000 but less than 20,000 population but largest town in a sparsely populated region | ||
| Bray | >20,000 population | ||
| Carlow | >20,000 population | ||
| Castlebar | >10,000 but less than 20,000 population but largest town in a sparsely populated region | ||
| Cavan | >10,000 but less than 20,000 population but largest town in a sparsely populated region | ||
| Celbridge | >20,000 population | ||
| Cork | >20,000 population | ||
| Derry | NI connection point close to border (may depend on NI greenway strategy) | ||
| Drogheda | >20,000 population | ||
| Dublin | >20,000 population | ||
| Dundalk | >20,000 population | ||
| Ennis | >20,000 population | ||
| Enniskillen | NI connection point close to border (may depend on NI greenway strategy) | ||
| Galway | >20,000 population | ||
| Kilkenny | >20,000 population |
| Primary NCN | Basis for inclusion | ||
|---|---|---|---|
| Nodes | |||
| Letterkenny | >10,000 but less than 20,000 population but largest town in a sparsely populated region | ||
| Limerick | >20,000 population | ||
| Longford | >10,000 but less than 20,000 population but largest town in a sparsely populated region | ||
| Mullingar | >20,000 population | ||
| Naas | >20,000 population | ||
| Navan | >20,000 population | ||
| Newbridge | >20,000 population | ||
| Newry | NI connection point close to border (may depend on NI greenway strategy) | ||
| Omagh | NI connection point close to border (may depend on NI greenway strategy) | ||
| Portlaoise | >20,000 population | ||
| Sligo | >10,000 but less than 20,000 population but largest town in a sparsely populated region | ||
| Strabane | NI connection point close to border (may depend on NI greenway strategy) | ||
| Swords | >20,000 population | ||
| Tralee | >20,000 population | ||
| Waterford | >20,000 population | ||
| Wexford | >20,000 population | ||
| Wicklow | >10,000 but less than 20,000 population but largest town in a sparsely populated region |
National Cycle Network Plan
Table 4.2: Secondary NCN Nodes
| Secondary | Basis for inclusion | ||
|---|---|---|---|
| Nodes | |||
| Arklow | >10,000 population | ||
| Ashbourne | >10,000 population | ||
| Athlone station | Rail transport hub | ||
| Balbriggan station | Rail transport hub | ||
| Ballina Station | Rail transport hub | ||
| Bettystown | >10,000 population | ||
| Carlow station | Rail transport hub | ||
| Carrigaline | >10,000 population | ||
| Castlebar station | Rail transport hub | ||
| Ceannt Station Galway | Rail transport hub | ||
| Clonmel | >10,000 population | ||
| Cobh | >10,000 population | ||
| Connolly Station | Rail transport hub | ||
| Cork Airport | Transport hub | ||
| Dublin Airport | Transport hub | ||
| Dublin Port | Facilitates passenger ferries / cruise ships | ||
| Dun Laoghaire Harbour | Facilitates passenger ferries / cruise ships | ||
| Ennis station | Rail transport hub | ||
| Enniscorthy | >10,000 population | ||
| Galway Harbour | Facilitates passenger ferries / cruise ships | ||
| Greystones | >10,000 population | ||
| Heuston Station | Rail transport hub | ||
| Kent Station Cork | Rail transport hub | ||
| Killarney | >10,000 population | ||
| Leixlip | >10,000 population | ||
| Longford Station | Rail transport hub | ||
| MacBride Station Drogheda | Rail transport hub | ||
| MacDiarmada Station Sligo | Rail transport hub |
| Secondary | Basis for inclusion | ||
|---|---|---|---|
| Nodes | |||
| MacDonagh Station Kilkenny | Rail transport hub | ||
| Malahide | >10,000 population | ||
| Mallow | >10,000 population | ||
| Maynooth | >10,000 population | ||
| Middleton | >10,000 population | ||
| Monaghan | >5000 but less than 10,000 population but largest town in the region | ||
| Mullingar station | Rail transport hub | ||
| Sallins & Naas station | Rail transport hub | ||
| Newbridge station | Rail transport hub | ||
| O Hanrahan Station Wexford | Rail transport hub | ||
| Plunkett Station Waterford | Rail transport hub | ||
| Port of Cork | Facilitates passenger ferries / cruise ships | ||
| Port of Waterford | Facilitates passenger ferries / cruise ships | ||
| Portlaoise Station | Rail transport hub | ||
| Roscommon | >5,000 but less than 10,000 population but largest town in the region | ||
| Rosslare Europort | Facilitates passenger ferries / cruise ships | ||
| Shannon Airport | Transport hub | ||
| Skerries | >10,000 population | ||
| Thurles | >5,000 but less than 10,000 population but largest town in a sparsely populated region | ||
| Tramore | >10,000 population | ||
| Tullamore | >10,000 population | ||
| Westport Station | Rail transport hub | ||
| Wicklow station | Rail transport hub |
National Cycle Network Plan
Step 2 – Identify Connections
Connections between nodes were established and links connecting the Primary and Secondary Nodes were developed. These connected primary nodes to adjacent primary and secondary nodes, as well as secondary nodes to adjacent primary nodes (either directly or via another secondary node).

Figure 4.2: NCN Nodes and Links
National Cycle Network Plan
Step 3 – Stakeholder Workshop: Destinations & Links
Workshops were held with key stakeholders to discuss and agree the nodes included in the NCN, as well as the proposed links between nodes. Stakeholders included the Department of Transport, the NTA, the CCMA, Fáilte Ireland, Sport Ireland, Cyclist.ie.
The discussions primarily revolved around defining primary and secondary nodes, and the density of the resulting cycle network. Initially, a population threshold of 10,000 or more was proposed for settlements, but it was deemed insufficient to provide comprehensive coverage. After engaging with stakeholders, it was unanimously agreed to lower the threshold to settlements with a population greater than 5,000 people. Additionally, transportation hubs such as train stations, airports, and ferry / cruise ship ports were identified as key nodes. Smaller settlements and other significant destinations like educational centers, recreational spots, and tourist attractions were classified as other nodes. This approach was agreed as it would lead to a suitably dense national network.
Step 4 – Identify Corridors
Once the NCN primary and secondary nodes were determined, the Links from Stage 2 were refined to develop corridors and corridor options connecting primary and secondary nodes. The purpose of this stage was to refine these links and to develop a series of corridor options. Corridor options were indicative alternatives of how to connect the primary and secondary nodes and aim to provide connections to other nodes (e.g., smaller settlements) where appropriate. An example of the corridor development approach is illustrated in Figure 4.3.
The identification of corridor options factored in multiple data sets using the NCN GIS dashboard developed for this purpose and targeted the use of existing or planned cycling (and other linear) infrastructure whenever possible.
Corridors connect:
Primary nodes (●) and Secondary nodes (●) ─
Corridors aim to incorporate:
Tertiary nodes, i.e., smaller settlements (●), centres of education, centres of employment, ─ leisure destinations, and tourist destinations
Existing cycle networks / infrastructure (–,–,–) ─
Planned cycle networks / infrastructure (–,–) ─
─ Other existing or natural resources, e.g., disused railways (—)

Figure 4.3: Example of Corridor Development — NCN GIS dashboard (left), proposed NCN corridor options (right)

Figure 4.3: Example of Corridor Development — NCN GIS dashboard (left), proposed NCN corridor options (right)
National Cycle Network Plan
Where more than one potential corridor alignment existed for a given linkage between two nodes, possible corridor options were assessed as outlined in Step 5 to identify the best performing option for inclusion in the NCN. Identified corridors were approximately 4km wide and did not include any design information.
Step 5 – Corridor Options Assessment
Where multiple options for NCN corridors had been identified, the performance of each option was determined by consideration against a range of assessment criteria as described below. The assessment of corridor options against these criteria was informed by a series of specific data sets as summarised in Table 4.3. Full details of the assessment approach, results and a list of the preferred corridor options are provided in Appendix E.
Table 4.3: Assessment Framework Summary Table
| NCN Plan Objectives | NCN Assessment | Data Set | ||
|---|---|---|---|---|
| Criteria | ||||
| Increase the number of cycle trips by improving the provision of safe and attractive cycling infrastructure. Connect to strategic destinations outside of urban areas as appropriate (including centres of education, centres of employment, and leisure destinations). | Commuter Trips | Database of smaller settlements between the 1,000 and 5,000 population (Other Nodes) | ||
| School Trips | Data base of Primary and Secondary Schools - Developed by AECOM | |||
| Leisure Trips | Data base of leisure facilities – including sports clubs and off-road trails - Developed by AECOM | |||
| Promote the design of cycling infrastructure that meets safety requirements. Promote the design of cycling infrastructure that provides a safe and secure environment for all users. | Potential Safety Impacts | National Transport Models Road Network showing flows in the form of AADT, posted speed limits and average speeds. | ||
| Integrate with existing and proposed cycling infrastructure (including greenways, safe routes to schools, the EuroVelo network, Interreg projects), as appropriate Incorporate existing greenways, disused railways, canals, bypassed national roads, regional and local roads, long distance trails, as appropriate. Propose corridors to maximise the number of users. Future-proof cycle route capacity, taking account of population growth and additional demand from modal shift. Connect to strategic destinations outside of urban areas as appropriate (including centres of education, centres of employment, and leisure destinations). | Integration with Existing Cycle Infrastructure | Database of existing cycle infrastructure – including greenways, Blueway’s and Eurovelo routes – developed by AECOM | ||
| Integration with Planned Cycle Infrastructure | Database of proposed cycle infrastructure – including greenways, Blueway’s and Eurovelo routes – developed by AECOM | |||
| Integration with Existing Infrastructure | Database of disused railways developed by AECOM | |||
| Integration with transport modes | Database of train stations - Developed by AECOM | |||
| Integration with Tourist Attractions | Fáilte Ireland database of tourist attractions with visitor numbers <200k total visitors in 2019. | |||
| Scenery and Route Attractiveness | ESRI Basemap |
National Cycle Network Plan
| NCN Plan Objectives | NCN Assessment | Data Set | ||
|---|---|---|---|---|
| Criteria | ||||
| Enhance local environments and biodiversity where possible (e.g., pollinator plans, green corridors). Support the development of cycling and walking culture in Ireland. | Impact on sensitive areas | Database of Special Protection Areas, Special Areas of Conservations and Proposed National Heritage Areas / National Heritage Areas and architectural conservation areas – Developed by AECOM. | ||
| Connect to strategic destinations outside of urban areas (including transport hubs and tourist destinations), as appropriate. | Social Inclusion | Pobal deprivation index - Developed by AECOM | ||
| Integration with Smaller Settlements | Database of smaller settlements between the 1,000 and 5,000 population (Other Nodes) | |||
| Gradient | ESRI Contour Maps |
Strategic Environmental Assessment (SEA) and Appropriate Assessment (AA) were integral to the option selection process.
SEA is a systematic process for evaluating the environmental consequences of proposed plans or programmes to ensure environmental issues are fully integrated and addressed at the earliest appropriate stage of decision making, with a view to promoting sustainable development. The assessment identified and evaluated the likely significant effects of each potential corridor option on an established baseline. The results of this assessment, contained in the SEA Environmental Report (Appendix G), was integral to the identification of the preferred corridor options.
An AA is an assessment of the potential adverse effects of a plan or project (in combination with other plans or projects) on the Natura 2000 network of European sites, i.e. Special Areas of Conservation (SACs) and Special Protection Areas (SPAs). Appropriate Assessment was integral to corridor assessment because likely significant effects cannot be dismissed alone, except for corridors 11 (Westport to Castlebar), 26 (Newcastle West to Tralee / Limerick), 57 (Newbridge to Naas) and 68 (Naas to Dublin), which could be screened out of AA because there are no European sites within the 4km corridors. The AA concluded that the flexible nature of the proposed NCN corridors provides the ability for all final cycle routes to be designed in such a way as to minimise and potentially avoid impacts rendering them non-significant, so long as the mitigation measures and development process outlined in the NIS, and summarised in Section 7.6, are employed.
The Appropriate Assessment is provided as part of the Natura Impact Statement in Appendix I.
Step 6 – Stakeholder Workshop
Having successfully completed Step 5, a comprehensive network of individual corridors between NCN Nodes was identified. The proposed corridors were those that best served the needs of the local community , having the potential to provide for the highest number of cycling trips and aligning with the objectives of the NCN Plan.
The next step in the NCN development process was to hold a series of workshops to discuss the network and allow stakeholders raise any potential issues. Stakeholders included the Department of Transport, the NTA, the CCMA, Fáilte Ireland, Sport Ireland, Cycling Ireland, Cyclist.ie.
The discussions focused on the process used to develop the corridors and a review of the resulting network. The issue of network coverage on the west coast was again highlighted but reviewing the proposed NCN in the context of other existing and planned cycle infrastructure (i.e., EuroVelo routes and greenways) it was agreed that the coverage and density of the corridor options presented achieved the project objectives and provided the intended core network.
National Cycle Network Plan
Step 7 – Public Consultation
The emerging NCN network was presented for public consultation to solicit the public’s views and opinions on the identified nodes and corridors and gain valuable feedback. Many of the stakeholders involved in previous workshops also submitted detailed feedback on the proposed NCN.
Some of the main points raised by submissions received during the public consultation in relation to the proposed network included:
Expanding the network to include additional greenways and rural settlements.
Incorporating (and upgrading) existing (and proposed) cycle infrastructure where possible.
Integrating with local cycle networks and connect town centres.
Feedback from public consultation was incorporated during finalisation of the NCN Plan and is included in Appendix C of this report.

Figure from page 43
| Feedback on NCN Propo | ||
Pages 34–43 · View in original PDF