7.3 Phased Implementation
7.3Phased Implementation
Implementation of the NCN Plan will be across three phases from 2023 to 2040, as follows:
Phase 1 – 2023 to 2025.
Phase 2 – 2026 to 2030.
Phase 3 – 2031 to 2040.
Funding and resource availability will dictate the speed of roll out of the network and the following principles have been applied in identifying how much of the network can be delivered in the various phases:
The NCN will be funded in accordance with the National Development Plan funding envelopes for the period up to and including 2030. In effect this means that circa €60m per annum will be available for the Greenways Programme and the rural elements of the NCN. Urban elements of the NCN will be funded and delivered through the NTA active travel programmes.
For the period post 2030, the level of funding which will be available for the NCN is unknown. As such, certain assumptions have been made around delivery of the NCN which will need to be reviewed once clarity around funding levels are available.
As noted in Section 7.2 above, base cost assumptions in this report are based on 2022 costs only. In order to identify the length of network which could be delivered by 2030, an average annual inflation of 3% per annum has been assumed.
Within the constraints identified above and in order to prioritise which corridor will be progressed in each phase, a two-step approach was taken. Firstly, a high-level multi-criteria analysis (MCA) was undertaken to rank each corridor. The criteria used, summarised in the table below, were developed based on the NCN vision and priorities for delivery. Each corridor was scored and ranked against all other routes.
Table 7.3: Route Implementation Criteria
| Criteria | Metrics |
|---|---|
| Demand 1 | Corridors were scored based on the scale of potential demand. The population served by the corridor was used as a proxy, this included the population of the nodes at either end of the corridor, as well as the populations of any settlements within the 4km wide corridor. Priority was given to corridors which served higher total populations. |
| Demand 2 | Consideration was given to the number of attractors and destinations along each route. This included activities, attractions, schools and sports facilities and was determined on a per kilometre basis, to avoid bias towards longer routes. |
| Route Length | Considering the initial focus on quick wins, shorter routes were scored higher. |
| Planning Status | Routes were scored based on their planning status, i.e., their current stage of project delivery. The highest score possible was given to routes that already exist and could be incorporated into the NCN immediately (although ancillary work may be required to bring them up to the required standard). Higher scores were given to routes that are already in planning, have secured funding, or have commenced design. |
| Network Coherence | Routes on the NCN that intersect existing routes will provide a greater level of network coherence. For each NCN route, the total length of other cycle routes within a 2km buffer was therefore determined. Routes with a greater total length were ranked higher. |
National Cycle Network Plan
| Criteria | Metrics |
|---|---|
| Safety | The NCN is intended to provide safe facilities for cyclists. High traffic speeds and traffic volumes reduce the perception of safety for cyclists. As such, priority was given to corridors with high traffic speeds and / or volumes, to improve the existing situation in terms of actual and perceived safety. |
| Social Benefits | Higher scores were given to routes with higher social benefits for example routes serving areas with high social deprivation scores or those serving areas that do not have an existing public transport service. |
Once the corridors were ranked, the second step was to further analyse and break them down into distinct sub-projects based on known or assumed data. Another sifting exercise was carried out to allocate the routes into different delivery phases. The sifting process took account of several further criteria, as follows:
Current Status – Projects currently underway on the NCN were prioritised as early delivery projects in the implementation phases, for example:
─ Existing cycle infrastructure that connects NCN nodes are included in Phase 1.
─ Similarly, greenways at construction stage are also included in Phase 1
─ Certain planned greenways that are in the advanced planning stage (i.e., anticipate seeking planning consent before the end of 2025) are included in Phase 2.
Cost / Resource Availability – Based on the funding and resource availability noted previously, an assessment was carried out of how much of the network could be delivered in Phases 1 & 2, with the balance being delivered in Phase 3 (subject to future funding and resource availability). Account was also taken of the need to continue to deliver greenway projects which do not form part of the NCN but are necessary for purely recreation and tourism purposes.
Geographic Spread – As this is a national network, consideration was given to achieving a balanced delivery nationally.
Following the assessment of each route against these criteria, a phased implementation plan was developed. At the end of the process, the three delivery phases and the approximate length of NCN to be delivered during each was identified, as outlined in Table 7.4.
Table 7.4: Implementation Phases
| Total | ||||
|---|---|---|---|---|
| Phase 1 | Phase 2 | Phase 3 | ||
| (2023-2025) | (2026-2030) | (2031-2040) | ||
| Approximate Kilometres Delivered | 330km | 660km | 2,510km | 3,500km |