1 Executive Summary
This Progress Report provides detail on the completion in 2026 of delayed or legacy
actions from previous iterations of the Climate Action Plan (CAP). In total, 10 of the 74
legacy actions were delivered by the end of Q2 2026 (Table 1). High impact actions
completed include: 2nd Circular Economy Strategy published; 200km of cycling
infrastructure completed; biofuel blend rates increased; Land Use Review Phase 2 report
published and a new National Demand Management Strategy for transport issued.
Completion of these legacy actions represents a significant milestone in Ireland’s climate
action journey, each being a meaningful high impact measure traced across from
previous Climate Action Plans. It is important to recognise their completion as these
actions experienced unexpected challenges and delays in delivery.
Overall implementation to date of CAP23, CAP24 and CAP25 legacy actions is outlined
in Table 2.
Notwithstanding this notable progress, delays in the delivery of remaining legacy actions
are attributed to several factors. This includes issues of alignment (waiting for
developments in other national policies, actions or EU legislation); capacity constraints
(internal resourcing and reliance on external consultants); technical complexity
(scale/type of project); consultation needs (stakeholders, public, internal etc) and other
discrete issues (e.g. funding and procurement). These delays threaten Ireland’s ability to
meet binding emissions reduction targets and risk increasing future climate changes,
compliance costs, and reputational harm. While much has been achieved and delivered
through successive CAPs, increased effort is required if Ireland is to close the gap to
meeting targets that it has agreed to. All delayed legacy actions will continue to be
reported on to maintain visibility on their delivery.
To provide more detail on progress, this report is organised into sectoral chapters in
order of emissions share, with a further chapter on cross-cutting activity. As in previous
progress reports, attention is given to Key Performance Indicators (KPIs) and the latest
emissions estimates and projections released by the EPA. Information on each reportable
action is contained at Appendix 1.
Table 1: Breakdown of Legacy Actions by Lead Department
| Department | Total Legacy | Completed in | Completed in | Delayed | ||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Actions | Q1 2026 | Q2 2026 | ||||||||
| DAFM | 4 | 0 | 0 | 4 | ||||||
| D/Transport | 18 | 4 | 0 | 14 | ||||||
| DCEE | 42 | 3 | 3 | 36 | ||||||
| DHLGH | 4 | 0 | 0 | 4 | ||||||
| DFHERIS | 1 | 0 | 0 | 1 | ||||||
| DETE | 2 | 0 | 0 | 2 | ||||||
| DPENDR | 3 | 0 | 0 | 3 | ||||||
| TOTAL | 74 | 7 | 3 | 64 |
Table 2: Breakdown of Legacy Actions by Sector
| Department | Total Legacy | Completed in | Completed in | Delayed | ||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Actions | Q1 2026 | Q2 2026 | ||||||||
| Agriculture | 2 | 0 | 0 | 2 | ||||||
| Transport | 18 | 4 | 0 | 14 | ||||||
| Electricity | 12 | 1 | 2 | 9 | ||||||
| Buildings | 10 | 0 | 0 | 10 | ||||||
| Industry | 1 | 0 | 0 | 1 | ||||||
| LULUCF | 4 | 0 | 1 | 3 | ||||||
| Cross-cutting | 27 | 2 | 0 | 25 | ||||||
| Total | 74 | 7 | 3 | 64 |
Table 3: Overall implementation of CAP23, CAP24 and CAP25 Legacy Actions
| Climate Action | Total Legacy Actions | Completed | Delayed | ||
|---|---|---|---|---|---|
| Plan | |||||
| CAP23 | 14 | 3 | 11 | ||
| CAP24 | 23 | 2 | 21 | ||
| CAP25 | 37 | 5 | 32 |