12.3 Emissions Projections for Electricity

In November 2023, the SEAI published their annual energy projections. Key conclusions for the electricity sector include:

Significant progress has been made to date when it comes to decarbonising our electricity system, with the carbon intensity of electricity from the grid decreasing by over 50% between 2005 and 2020;

In all modelled scenarios presented in this chapter, variable renewables are the largest input to electricity generation by 2030, with a sharp increase anticipated later in this decade due to assumed connection of large offshore wind projects;

The deployment of renewables needs to outpace the growth in energy demand for it to deliver the absolute reductions in GHG emissions required. Therefore, the timing of the delivery of the renewable energy generation relative to the scale and pace of growth in electricity demand is a critical factor.

Analysis from the SEAI to support the electricity measures set out in this Climate Action Plan shows that:

It will be extremely challenging to meet the electricity emissions ceilings for carbon budget periods 1 and 2.

Delivery and integration of onshore and offshore wind and solar PV is the bestperforming mitigation measure to deliver emissions abatement at scale and at speed. Already under the first Climate Action Plan in 2019, reaching 70% renewables by 2030 provided the core of emissions reduction in the sector. Increasing renewables to 80% of demand under Climate Action Plan 2021 and beyond this to the CAP23 capacity targets of 22 GW of wind and solar achieves a further 16% emissions reductions over the first two carbon budgets. No other supply side measure comes close to the emissions abatement achieved by the early and rapid deployment of unprecedented wind and solar capacity.

Achieving the CAP 23 renewable energy capacity of 9 GW of onshore wind, 8 GW of solar and 5 GW of offshore wind can deliver circa 10 Mt of emissions abatement reduction over the first two carbon budgetary periods. Only the reduction of electricity demand to an extent that would drastically undermine Ireland’s long term economic development, society, and public welfare would be capable of the level of emissions reduction that solar PV, onshore and offshore wind can provide.

Accelerating Indigenous Renewables to reduce Emissions and bolster Energy Security

Given that the programme of large-scale offshore wind deployment is expected to be realised towards end decade, deployment rates for onshore renewables will need to increase to match demand growth to ensure we keep electricity emissions within range of the carbon budgets. This requires a major upscaling and accelerating in current deployment of renewables, particularly onshore wind.

As an example, the historical average deployment of onshore wind installed capacity connected between 2008 and 2020 inclusive was ~280 MW per annum from 19 projects (with an annual maximum of 612 MW). To achieve the necessary emissions abatement, an approximately eight-times increase of renewable energy deployment to 2.3 GW annually would be needed between 2024 and 2030.

Achieving these deployment rates requires accelerating across the three pillars of renewables delivery – grid, planning, and route to market. Delivery of the electricity network and supporting grid connection policy need to urgently align to support the rapid roll out of renewables. As importantly, greater alignment between local plans and renewable energy targets at national and regional level to support investment in and delivery of onshore wind and solar renewable energy is also critical.

The ongoing revision of the National Planning Framework, the Renewable Electricity Spatial Planning Framework and the implementation of the recast Renewable Energy Directive, including the mapping of Renewable Acceleration Areas, will support these.

Finally, a supportive investment climate for renewables in Ireland is essential through the flagship Renewable Electricity Support Scheme and the Accelerating Renewable Electricity Taskforce. Grid delivery and a supportive planning framework are both critical drivers of the investment needed in the sector as Ireland is competing for international capital and in securing supply chains as global efforts to scale up renewables intensify. Factors that lead to lower renewables deployment rates increase the risk that the electricity emissions will be out of range of the carbon budget programme with implications for future carbon budget periods and other sectors.

Government is overseeing a phased approach to offshore wind development. The Offshore Wind Delivery Taskforce has been established to drive delivery and capture the wider and longer-term economic and business opportunities associated with the development of offshore renewables in Ireland.

To deliver on the roadmap for renewables set out in CAP23, the Accelerating Renewable Electricity Taskforce has been established to coordinate the fast-track and increased deployment and output of renewable electricity generation and supporting technologies in the near-term.

Notwithstanding the above, the scale of projected electricity demand growth means that the delivery and integration of the renewables programme alone does not deliver required levels of emissions reduction. Net Zero demand growth and calibrating renewable energy with demand will need to be pursued as a matter of urgency as a part of a longer-term decarbonisation pathway for the sector including for the third carbon budget.