In total, 20 of the 33 new actions due to date under CAP24 have been completed. The

progress of high impact actions delayed from CAP 2023 is also included in this Report,

with 21 of 47 reportable legacy actions3 completing in the first half of 2024.

Delivery by responsible Department for new actions due in the first half of 2024 is detailed in

Table 1. Table 2 outlines Departmental delivery on legacy CAP23 actions. Table 3 details action

implementation by sector to date, reflective of the whole-of-government effort required to

reduce emissions across our economy and society.

Table 1 Delivery by Department on new Q1 and Q2 2024 actions

DepartmentCompleted Q1 and Q2 actionsTotal no. of new actions due
DECC1320
DAFM13
D/Transport35
DHLGH02
DFHERIS33
TOTAL2033

Table 2 Delivery by Department on legacy CAP23 actions due for reporting in 2024

DepartmentCAP23Discontinued Legacy ActionOn Schedule Legacy ActionTotal Legacy actions due
Legacy
actions
complete
DECC90024
DAFM 32104
DHLGH2006
D/Transport 33017
DPENDR1002
DETE3004
D/Taoiseach0001
DFA1001
TOTAL211149

3Note, as per Table 2, that one additional legacy action published in Q4 2023 from D/Transport is considered to be ‘on schedule’ in keeping with EU negotiations, and will thus be removed from the legacy exercise next quarter and reported on instead later in the year. Another legacy action has been discontinued by DAFM and so could not be attributed as ‘complete’ or ‘delayed’ in progress reporting and will also be removed from reporting in Q3.

Table 3 Delivery by Sector by end of Q2 2024 (including delayed high impact CAP23 actions)

SectorCompleteTotal actions due
Agriculture36
Transport712
Electricity715
Buildings210
LULUCF23
Industry46
Cross-Cutting1628
TOTAL4180