In total, 39 actions are reported as delayed in the first half of 2024, including 13 from CAP24

and 26 legacy high impact actions from CAP23. The most common reasons reported by

Departments for delivery delays include:

Need for further stakeholder engagement, including public consultation or internal consensus building

within working groups, departments and agencies;

Layers of administrative clearance, whereby actions are significantly advanced and are awaiting final

approval or publication (e.g. final drafts have been prepared or schemes are awaiting final launch) and

expect completion in Q3;

Issues of sequencing and alignment, whereby the completion of actions is reliant on the finalisation of

another activity or policy both at national and/or EU levels; and

Capacity and capability constraints, including internal resourcing issues and procurement delays arising

from a reliance on external expertise for climate policy or scheme development; and/or

Unexpected legal or technical complexity, often leading to the need for extra time for additional research,

outreach, legal drafting, and/or the development of new working approaches.

Delays in climate action delivery must be urgently overcome to work towards emissions

reduction targets at international, EU and national levels. Failure to complete climate

actions now will result in steeper trajectories and decarbonisation pathways to bring

sectors, society and the Irish economy back on track.