EL │Electricity
EL │Electricity
| Theme: Accelerate Renewable Energy Generation | 2025 KPI: 50% renewable electricity share of demand. 6 GW onshore wind capacity Up to 5 GW solar PV capacity, including at least 1 GW of new non-utility solar | 2025 Abatement Potential: 1.3 MtCO eq. 2 | ||||
|---|---|---|---|---|---|---|
| Measure: Accelerate Renewable Energy Generation | ||||||
| Actions | ||||||
| Action Number | Actions | Steps necessary for delivery | Output | Timeline | Lead | Stakeholders |
| EL/24/1 | Accelerating Renewable Electricity Taskforce to publish programme of work | As per headline action | Programme of Work Published | Q2 2024 | TF, DECC | DHLGH, DPENDR, D/Taoiseach, ESBN, EirGrid, CRU, NTMA |
| EL/24/2 | Offshore Wind Delivery Taskforce to publish key actions for 2024 | As per headline action | Key Actions published | Q1 2024 | TF, DECC | 8 Departments, WEI, MARA, EI, CRU, SEAI, EirGrid, Irish Marine Institute |
| EL/24/3 | Revision to the National Planning Framework to include regional capacities for the allocation of national targets at a regional level in order to inform local development plan policy | As per headline action | National Planning Framework published | Q3 2024 | DHLGH | DECC |
|---|---|---|---|---|---|---|
| EL/24/4 | Publish Regional Renewable Electricity Strategies | As per headline action | Strategies Published | Q4 2024 | Regional Assemblies | DECC, DHLGH, SEAI |
| EL/24/5 | Publish Revised Wind Energy Development Guidelines for onshore wind | As per headline action | Guidelines published | Q1 2025 | DHLGH | DECC |
| EL/24/6 | Publish revised methodology for Local Authority Renewable Energy Strategies | As per headline action | Methodology published | Q2 2024 | SEAI | DECC |
| EL/24/8 | Deliver onshore and offshore RESS auctions as per the annual RESS auction calendar | As per headline action | Auctions held annually | Q4 2024 | DECC | CRU, EirGrid |
| EL/24/9 | Develop a Private Wires Policy Framework | As per headline action | Framework developed | Q4 2024 | DECC | - |
| EL/24/11 | Implement Hybrid Connection Roadmap | As per headline action | Hybrid Connections to grid possible | Q4 2024 | CRU (Reporting lead: DECC) | ESBN, EirGrid |
| Theme: Accelerate Flexibility | 2025 KPI: Maximum level of renewables at any one time on the grid: 85%. Dispatch down (excluding oversupply) of renewables below 7%. Minimise oversupply. Required long term storage (4 hour plus) in place | 2025 Abatement Potential: Abatement is included in the Accelerate Renewable Energy Generation figure | ||||
|---|---|---|---|---|---|---|
| Measure: Accelerate Flexibility | ||||||
| Actions | ||||||
| Action Number | Actions | Steps necessary for delivery | Output | Timeline | Lead | Stakeholders |
| EL/24/16 | Adopt Electricity Storage Policy Framework | As per headline action | Actions for 2024 Delivered | Q4 2024 | DECC | - |
| EL/24/17 | Reduce the minimum number of conventional synchronous generation units from 8 to 7 to facilitate higher levels of renewables on the system and a reduction in carbon emissions from non-renewable generation | As per headline action | Reduction in synchronous units from 8 to 7 | Q2 2024 | EirGrid, (Reporting lead: DECC) | - |
| EL/24/18 | Issue suite of recommendations papers on market options to incentivise low/no carbon flexible demand from the electricity sector | As per headline action | Issue Recommendations papers to CRU | Q4 2024 | EirGrid, (Reporting lead: DECC) | CRU, DECC, ESBN |
| Theme: Demand Management | 2025 KPI: Demand side flexibility 15-20% Zero carbon demand growth | 2025 Abatement Potential: 0.86 MtCO eq. 2 | ||||
|---|---|---|---|---|---|---|
| Measure: Demand Management | ||||||
| Actions | ||||||
| Action Number | Actions | Steps necessary for delivery | Output | Timeline | Lead | Stakeholders |
| EL/24/21 | Decision on Dynamic Green Electricity tariffs | As per headline action | CRU Decision paper published | Q2 2024 | CRU (Reporting lead: DECC) | - |
| EL/24/22 | Implementation of enhanced emissions reporting framework for electricity emissions for large energy users and the system operators dispatch actions | As per headline action | Regular reporting | Q4 2024 | SEAI/CRU/EirGrid/ESBN (Reporting lead : DECC) | DETE, IDA, DECC |
| EL/24/23 | Incentivise and enable large energy users to participate in flexible demand initiatives designed to enable low / zero carbon demand growth | As per headline action | New incentives introduced for LEUs | Q2 2024 | ESBN (Reporting lead: DECC) | CRU |
| EL/24/24 | Create a route to market for medium and long duration storage facilities which can provide flexible demand | As per headline action | Market mechanism for firms to develop long duration storage facilities started | Q3 2024 | CRU, EirGird (Reporting lead: DECC) | ESBN |