Theme: Accelerate Renewable Energy Generation2025 KPI: 50% renewable electricity share of demand. 6 GW onshore wind capacity Up to 5 GW solar PV capacity, including at least 1 GW of new non-utility solar2025 Abatement Potential: 1.3 MtCO eq. 2
Measure: Accelerate Renewable Energy Generation
Actions
Action NumberActionsSteps necessary for deliveryOutputTimelineLeadStakeholders
EL/24/1Accelerating Renewable Electricity Taskforce to publish programme of workAs per headline actionProgramme of Work PublishedQ2 2024TF, DECCDHLGH, DPENDR, D/Taoiseach, ESBN, EirGrid, CRU, NTMA
EL/24/2Offshore Wind Delivery Taskforce to publish key actions for 2024As per headline actionKey Actions publishedQ1 2024TF, DECC8 Departments, WEI, MARA, EI, CRU, SEAI, EirGrid, Irish Marine Institute
EL/24/3Revision to the National Planning Framework to include regional capacities for the allocation of national targets at a regional level in order to inform local development plan policyAs per headline actionNational Planning Framework publishedQ3 2024DHLGHDECC
EL/24/4Publish Regional Renewable Electricity StrategiesAs per headline actionStrategies PublishedQ4 2024Regional AssembliesDECC, DHLGH, SEAI
EL/24/5Publish Revised Wind Energy Development Guidelines for onshore windAs per headline actionGuidelines publishedQ1 2025DHLGHDECC
EL/24/6Publish revised methodology for Local Authority Renewable Energy StrategiesAs per headline actionMethodology publishedQ2 2024SEAIDECC
EL/24/8Deliver onshore and offshore RESS auctions as per the annual RESS auction calendarAs per headline actionAuctions held annuallyQ4 2024DECCCRU, EirGrid
EL/24/9Develop a Private Wires Policy FrameworkAs per headline actionFramework developedQ4 2024DECC-
EL/24/11Implement Hybrid Connection RoadmapAs per headline actionHybrid Connections to grid possibleQ4 2024CRU (Reporting lead: DECC)ESBN, EirGrid
Theme: Accelerate Flexibility2025 KPI: Maximum level of renewables at any one time on the grid: 85%. Dispatch down (excluding oversupply) of renewables below 7%. Minimise oversupply. Required long term storage (4 hour plus) in place2025 Abatement Potential: Abatement is included in the Accelerate Renewable Energy Generation figure
Measure: Accelerate Flexibility
Actions
Action NumberActionsSteps necessary for deliveryOutputTimelineLeadStakeholders
EL/24/16Adopt Electricity Storage Policy FrameworkAs per headline actionActions for 2024 DeliveredQ4 2024DECC-
EL/24/17Reduce the minimum number of conventional synchronous generation units from 8 to 7 to facilitate higher levels of renewables on the system and a reduction in carbon emissions from non-renewable generationAs per headline actionReduction in synchronous units from 8 to 7Q2 2024EirGrid, (Reporting lead: DECC)-
EL/24/18Issue suite of recommendations papers on market options to incentivise low/no carbon flexible demand from the electricity sectorAs per headline actionIssue Recommendations papers to CRUQ4 2024EirGrid, (Reporting lead: DECC)CRU, DECC, ESBN
Theme: Demand Management2025 KPI: Demand side flexibility 15-20% Zero carbon demand growth2025 Abatement Potential: 0.86 MtCO eq. 2
Measure: Demand Management
Actions
Action NumberActionsSteps necessary for deliveryOutputTimelineLeadStakeholders
EL/24/21Decision on Dynamic Green Electricity tariffsAs per headline actionCRU Decision paper publishedQ2 2024CRU (Reporting lead: DECC)-
EL/24/22Implementation of enhanced emissions reporting framework for electricity emissions for large energy users and the system operators dispatch actionsAs per headline actionRegular reportingQ4 2024SEAI/CRU/EirGrid/ESBN (Reporting lead : DECC)DETE, IDA, DECC
EL/24/23Incentivise and enable large energy users to participate in flexible demand initiatives designed to enable low / zero carbon demand growthAs per headline actionNew incentives introduced for LEUsQ2 2024ESBN (Reporting lead: DECC)CRU
EL/24/24Create a route to market for medium and long duration storage facilities which can provide flexible demandAs per headline actionMarket mechanism for firms to develop long duration storage facilities startedQ3 2024CRU, EirGird (Reporting lead: DECC)ESBN