In total, 102 actions were delayed under CAP23 (c.35% of actions due by the end of Q4

2023). The most common reasons reported by Departments for delivery delays in Q4

include:

Capacity and capability constraints, most notably related to resourcing (e.g.

staffing, funding, ownership and recruitment) as well as procurement delays arising

from a reliance on external expertise for climate policy ideation and development;

Unexpected complexity, often leading to the need for extra time for additional

research or review before an action can be completed;

Awaiting final approval or publication, whereby actions are significantly advanced

and expect completion early in 2024;

Issues of sequencing and alignment, whereby completion of some actions is

reliant on the completion of other activity, negotiations or policy before they can

progress;

Additional time required for further stakeholder engagement, including public

consultation and clearance with interdepartmental working groups; and

Change of approach, whereby an alternative method or pathway has been decided

for an action since the publication of CAP23 with more time required to build

consensus, achieve buy-in or establish new structures.

Delays in climate action delivery must be urgently overcome to meet legally binding

emissions reduction targets at international, EU and national levels. Failure to complete

climate actions now will result in steeper trajectories and decarbonisation pathways to bring

sectors, society and the economy back on track.

The legacy exercise accompanying this progress report (Appendix 2) identifies 49 high

impact delayed actions that will carry forward for delivery and reporting in Q1 2024 (and

beyond, as required) to maintain commitment to their completion. The other 53 lower impact

delayed actions from CAP23 are closed off from continued centralised reporting in Appendix

2, with explanation as to how continued progress will be ensured (e.g. by Agency,

Department or by Taskforce), any changes in approach necessary and/or how CAP24

subsumes or overrides the action but maintains ambition.

Further detail on high impact actions due in Q4 is provided next through sectoral chapters.

Detail on all reportable actions completed and delayed this quarter is at Appendix 1.

Pages 10–11 · View in original PDF