    Request Reference a consequence of the Bandon FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 15. Can you confirm if there are any legal costs, or provision for future legal costs, arising from proceedings where the
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Bandon FRS is mentioned?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 1. Can you confirm the Investment to Date (ITD) on the Skibbereen Flood Relief Scheme (FRS)?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference in respect of the Skibbereen FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 3. Can you confirm the latest forecast for the final Construction Cost for the Skibbereen FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 4. Can you confirm the Agreed Contract Sum, at signing, for the Main Contractor on the Skibbereen FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Skibbereen FRS and what budgetary provision has been made for outstanding Claims or Adjustment Events Notices from
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference the Main Contractor the Skibbereen FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 6. Can you confirm the amount that has been certified on Contractor Claims or Adjustment Events on the Skibbereen
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 7. Can you confirm the latest revised forecast for the Capital Cost at Completion for the Skibbereen FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 8. Can you confirm the latest forecasted Project Cost for the Skibbereen FRS i.e. the Project Cost that is comparable to
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference the Project Cost utilised in the original Cost – Benefit Analysis for which approval was sought to proceed with the
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Skibbereen FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 9. Can you confirm if the annual maintenance budget for the Skibbereen FRS has been finalised and/or the current/
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 10. Can you confirm the Ministerial approval figure for the Skibbereen FRS Budget and please clarify if this figure is to
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference cover Capital Cost only?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Skibbereen FRS, the amount certified and paid (accounted for in ITD) to these Engineering Consultants and the total
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference budget to completion for Engineering Services on the Skibbereen FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 12. Can you confirm if a retrospective Cost-Benefit Analysis been undertaken for the Skibbereen FRS post hand-over of
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference the scheme from the Contractor for operation or post Completion of the Capital Works Contract? If yes, can you confirm
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference the outcome of this analysis?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 13. Can you clarify if additional costs to the Construction, Capital and Project Budget and arising from the Skibbereen FRS
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference a consequence of the Skibbereen FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Skibbereen FRS is mentioned?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 1. Can you confirm the Investment to Date (ITD) on the Clonakilty Flood Relief Scheme (FRS)?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference in respect of the Clonakilty FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 3. Can you confirm the latest forecast for the final Construction Cost for the Clonakilty FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 4. Can you confirm the Agreed Contract Sum, at signing, for the Main Contractor on the Clonakilty FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Clonakilty FRS and what budgetary provision has been made for outstanding Claims or Adjustment Events Notices from
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference the Main Contractor the Clonakilty FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 6. Can you confirm the amount that has been certified on Contractor Claims or Adjustment Events on the Clonakilty FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 7. Can you confirm the latest revised forecast for the Capital Cost at Completion for the Clonakilty FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 8. Can you confirm the latest forecasted Project Cost for the Clonakilty FRS i.e. the Project Cost that is comparable to the
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Project Cost utilised in the original Cost – Benefit Analysis for which approval was sought to proceed with the Clonakilty
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 9. Can you confirm if the annual maintenance budget for the Clonakilty FRS has been finalised and/or the current/
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 10. Can you confirm the Ministerial approval figure for the Clonakilty FRS Budget and please clarify if this figure is to
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Clonakilty FRS, the amount certified and paid (accounted for in ITD) to these Engineering Consultants and the total
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference budget to completion for Engineering Services on the Clonakilty FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 12. Can you confirm if a retrospective Cost-Benefit Analysis been undertaken for the Clonakilty FRS post hand-over of the
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 13. Can you clarify if additional costs to the Construction, Capital and Project Budget and arising from the Clonakilty FRS
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference a consequence of the Clonakilty FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Clonakilty FRS is mentioned?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference Togher and Douglas is the same scheme. I wish to request the following information and supporting documentation
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference pursuant to Environmental Information Directive and Regulations (AIE) and Freedom of Information legislation (FOI):
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 1. Can you confirm the Investment to Date (ITD) on the Togher Flood Relief Scheme (FRS)?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference in respect of the Togher FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 3. Can you confirm the latest forecast for the final Construction Cost for the Togher FRS?
    Requester Type
    Office of Public Works
  • Received
    Decided
    Request Reference 4. Can you confirm the Agreed Contract Sum, at signing, for the Main Contractor on the Togher FRS?